Texas Parks and Wildlife Commission
Contract Number | Vendor Name | Type of Contract | Reason for Change | Original Term Date | Revised Term Date (if applicable) | Original Contract Amount | Revised Contract Amount (if applicable) | Percentage Change | Purchaser | Date Entered |
---|---|---|---|---|---|---|---|---|---|---|
445701 | A & E Welding | Internal Repair | Differences in lift cylinders required the vendor to custom build a sub-frame and brackets to mount cylinder pivots. | 3/15/2014 | No Change | $2,500.00 | $4,450.00 | 78.00% | Judy Ahrens | 3/7/2014 |
446204 | Republic Services | Disposal Services | Final disposal costs exceeded original estimate due to amount of materials and administrative fees. | 2/28/2014 | No Change | $400.00 | $534.49 | 33.62% | Judy Ahrens | 3/17/2014 |
444328 | Mustang Power Supplies | Internal Repair | Additional work needed for engine on vessel. After cylinder heads were re-installed, engine was tested and found to have a cracked cylinder head which leaked water into the engine. Additional charges are for parts and labor to replace cylinder heads. | 1/13/2014 | 6/14/2014 | $4,500.00 | $25,517.00 | 467.04% | Linda Martinez | 3/24/2014 |
447773 | TIBH | Term | TIBH shipped 2 extra cases of trash can liners ordered on line 1 of PO-park decided to keep additional cases. | 8/15/2014 | No Change | $730.70 | $856.10 | 17.16% | Mary Cunningham | 3/7/2014 |